  1. Proponent submits revised Plan of Operations [Sep 2014]
  2. Federal Register Notice of Intent to prepare EIS [Mar 2016]
  3. Public scoping period and scoping meetings
    [5 meetings between Mar-Jun 2016; comment period extended from 60 days to 120 days, closed Jul 18, 2016 ]
  4. Compile and review existing data
  5. Prepare project description and identify project alternatives
  6. Publish Alternatives Evaluation Report [Sep 2017]
  7. Validate Baseline Information; analyze environmental effects
  8. Prepare Draft EIS
  9. We Are Here
  10. Respond to public comments and prepare Final EIS
  11. Federal Register Notice of Availability of Final EIS and Draft ROD
  12. 45-day Public Objection Period
  13. Resolve objections to Final EIS and draft ROD
  14. Issue Final Record of Decision

Public Hearings

The Forest Service will host its remaining two public meetings in Queen Valley on October 8 and in Tempe on October 10.

Public Hearings

Video & Materials

A video presentation – the same information introduced at each public meeting – as well as meeting materials (posters and newsletter) are available for public review.

Video - Draft EIS

Public Meeting Materials

Draft EIS Released

The Draft Environmental Impact Statement (DEIS) for the Resolution Copper Project and Land Exchange is now available for review under the 'EIS Info' tab.

Draft EIS

Comment on DEIS

Optional ways to comment on the Draft EIS are located under the 'EIS Info' and the 'Public Involvement' tabs.

Comment

Media & General Info

Point of Contact
John Scaggs
Tonto National Forest
john.scaggs@usda.gov

Apache Leap Special Management Area
Apache Leap SMA website