Date Published
October 2020
Summary
The Skunk Camp TSF was indicated as the preferred alternative in the DEIS, which also included a mitigation measure (FS-227) to complete a “more robust and refined” Failure Mode and Effects Analysis (FMEA) risk assessment “with more refined designs and site-specific information,” to be conducted between the DEIS and the Final EIS to address dam safety comments.
Cited In
Reference Information
Gannett Fleming. 2020. Failure Modes and Effects Analysis 2020 Workshop: Resolution Copper Environmental Impact Statement, Proposed Skunk Camp Tailings Storage Facility. Prepared for BGC Engineering. Phoenix, Arizona: Gannett Fleming. October.