Summary
The Peg Leg Pipeline Corridor (PLPC) DEIS study considered two potential pipeline corridor alignment options for transport of mill tailings from the West Plant concentrator site to the Peg Leg TSF and return of reclaim water from the Peg Leg TSF back to the West Plant concentrator site.
Reference Information
Golder Associates Inc. 2018b. Peg Leg Pipeline Corridor DEIS Report. Tucson, Arizona: Golders Associates Inc. July 2.
Golder Associates Inc. 2018b. Peg Leg Pipeline Corridor DEIS Report. Tucson, Arizona: Golders Associates Inc. July 2.