Reclamation plan for the proposed TSF at the Skunk Camp site for the FEIS in part to address the mitigation measure (FS-226). The objective of this plan is to support the site-wide reclamation plan (Tetra Tech 2020) by providing the strategy and design for implementing closure measures for the Skunk Camp TSF.
The long-term closure goals for the Skunk Camp TSF are to have a stable facility and to limit the generation and potential release of poor water quality seepage. Management during operations of the potentially acid generating (PAG) pyrite tailings and their location within the facility post-closure is important to reducing the risk of acid rock drainage (ARD) and metals leaching (ML).
KCB Consultants. 2021. Resolution Copper Project: Skunk Camp TSF Reclamation Plan. Doc. # CCC.03-81600- EX-REP-00023 - Rev. 1. Phoenix, Arizona: KCB Consultants Ltd. May.