The purposes of this BE are: 1) to describe the physical and biological features of the Analysis Area, 2) to describe and map the plant communities, and 3) to identify the potential for special status species to occur within the Analysis Area.
This technical memorandum was prepared to summarize results of drilling, construction, and testing at hydrologic test well DHRES-09. The well was installed to characterize hydrogeologic conditions in the deep groundwater system west of the Concentrator Fault and east of the Main Fault, and to provide a monitoring point for the deep groundwater system during on-going dewatering operations. Monitoring data obtained from DHRES-09 have been incorporated into the RCM hydrologic monitoring program.
Arizona hedgehog cactus surveys were conducted within the Resolution Pre-Feasibility Activities area in conformance with the monitoring required by the Resolution Copper Mining Pre-feasibility Activities Plan of Operations EA and the Forest Service's Biological Assessment and Evaluation.
Phase I Environmental Site Assessment (ESA) for approximately 640 acres referred to as East Clear Creek. The property comprises the entirety of Section 9 in Township 14 North, Range 12 East relative to the Gila and Salt River Baseline and Meridian, in Coconino County, Arizona.
Flooding is among the worst natural disasters responsible for loss of life and property in Arizona, underscoring the importance of accurate estimation of flood magnitude for proper structural design and floodplain mapping. Twenty-four years of additional peak-flow data have been recorded since the last comprehensive regional flood frequency analysis conducted in Arizona. Periodically, flood frequency estimates and regional regression equations must be revised to maintain the accurate estimation of flood frequency and magnitude.
The proposed Resolution Mine presents a number of socioeconomic issues which required research, analysis and modeling. This report provides greater detail and documentation regarding the socioeconomic effects that will be summarized in the Draft EIS.
Resolution Copper Company commissioned Golder and Associates to establish a program for the collection of baseline surface water data near the future RCC mine and associated facilities. The intended uses of the data are primarily to support and EIS, develop a sound conceptual site model as a basis for predicting future impacts, and document current conditions as a baseline for judging future impacts.
This report summarizes the meteorological, nitrogen dioxide (NO2), sulfur dioxide (SO2), ozone (O3), and particulate matter (PM) data collected at the Resolution Copper Project near Superior, Arizona for the third quarter, July 1-September 30, 2013.
This tech memo has been prepared to summarize results of the Phase II field investigations of the Near West site, conducted in support of RCM's ongoing prefeasibility studies for storage of RCM mine tailings. The purpose of Phase II investigations was to conduct electrical resistivity surveys to assess the potential occurrence of shallow groundwater at the Near West site.
Three motion-sensitive cameras besides springs within a study area along Devils Canyon. Cameras captured numerous identifiable images of animals representing both mammals and bird species.